Thursday 18 September 2014

PROGRESS AS ON 24TH AUG 2014


Something technical worth noting here:

 

The tendon cables end looked like this. Note the black tube already cut off because the cable duct has already been grouted.



After the tendon cables have been tensioned, notice that the beam have deflected upwards at the centre, or huncing upwards due to the compression of concrete at the bottom of the beam.

 The gap between the casting floor and the deflected midspan of the beam is about 90 cm


The other end of the beam with the two end-caps for the cables.

 Progress of the retaining wall

Concrete of pile caps have nearly reached the full strength



And the Bambangan fruits have nearly gone. Who took them, well maybe the owner and the workers ?
 