Anyhow these are the progress that I have seen while passing the bridge everyday. The solid concrete retaining wall is already completed by now.
On 5 May 2013
Concreting using the crane 5 May
Concreting the pile caps which will support the prestress beams
from 12 May 2014
Progress of the retaining wall as on 12 May 2014
From 10 June 2014
Note the gunny sacks used to water-cure the prestressed beams - 3 beams completed up to this date.
and the bambangan fruits have grown - good enough for cooking fish with.
Bridge caps left bank completed
retaining wall half completed by 10 Jun 2014.