Workers installing the steel end caps for the prestress concrete beam
Seems that there are 12 strands of cables in the top duct while the bottom one has 18 strands.
Rebars and formwork for the pile cap cum abutment at the left bank
At the right bank, the installation of rebars for the concrete retaining wall had commenced
It was a hot day on the 28th April but this time the river water is flowing with red clay. Some earthworks must be carried out upstream