I got a feedback on this blog that my comments are too technical. Actually, after leaving the technical world for the last 2 years, I myself can hardly use technical terms or even name the parts of the bridge. However, should any readers have any questions, I will try to answer them, or make additions by editing the relevant post.
Well, as usual I will monitor the Bambangan. Hopefully if the fruits can grow, I may just ask the owner for a few ripe ones, that is if it can grow to maturity before the roots of the tree give way to the clay around it and dies.
For the moment I think the fruits have not reach one inch in size yet.
The formwork for the prestressed concrete beam have now been fixed. Note that it is made of prefabricated steel plates which is then joined together with bolts plus some extra supports just to prevent it from tumbling down during the filling up with concrete. As of today concreting work has not begun because the supporting bars are not fully installed according to the workers.
Here you can see that the steel formwork is sufficient for one beam only and there are 5 beams for the two lane bridge. Therefore the concrete for the first beam will have to set before the formworks are removed and re-used for the next beam and so forth. This type of concrete beam design must come in pre-selected sizes otherwise the production of the steel formworks would become an expensive business.
Also note the steel reinforcing bars juts out from the top of the beam in a T shape form. This part will be connected to the concrete bridge deck or slab once the beams are installed on top of the pile caps. The beam and slab then become a composite single structure.
Foreground, the workers have added the rebars to the final height of the pile caps where the ends of the beam will be laid on.
background: the works for the retaining wall continues.
Friday, 2 May 2014
Thursday, 1 May 2014
BRIDGE PROGRESS ON 28 APRIL 2014
Workers installing the steel end caps for the prestress concrete beam
Seems that there are 12 strands of cables in the top duct while the bottom one has 18 strands.
Rebars and formwork for the pile cap cum abutment at the left bank
At the right bank, the installation of rebars for the concrete retaining wall had commenced
It was a hot day on the 28th April but this time the river water is flowing with red clay. Some earthworks must be carried out upstream
BRIDGE PROGRESS 20 APRIL 2014
The Bambangan fruit is still small but growing.
Full view of one whole span of prestress concrete Beam
How the ends of the top and bottom cable is installed ( hooked and embedded) at one end of the concrete beam
End for mid cables sticking out of the cable duct which will be used for tensioning the cables later
Workers jointing the cable ducts, simple screw it and tape it.
The other end of the Beam where top and bottom cables are jutting out of the ducts that will be tensioned later, just like the tendons of your muscles !
Embedding of the ends of the middle cable,
Rebars for the left bank pile cap cum abutment
At right bank, earthworks continue to give space to the retaining wall
Left bank showing gabion protection works for the bridge piles, and the clear water in river during dry hot spell
Full view of one whole span of prestress concrete Beam
How the ends of the top and bottom cable is installed ( hooked and embedded) at one end of the concrete beam
End for mid cables sticking out of the cable duct which will be used for tensioning the cables later
Workers jointing the cable ducts, simple screw it and tape it.
The other end of the Beam where top and bottom cables are jutting out of the ducts that will be tensioned later, just like the tendons of your muscles !
Embedding of the ends of the middle cable,
Rebars for the left bank pile cap cum abutment
At right bank, earthworks continue to give space to the retaining wall
Left bank showing gabion protection works for the bridge piles, and the clear water in river during dry hot spell
Bridge Progress Photos 7 April 2014
First of all, the flowers of the Bambangan tree seems on their way to become fruits.
Left bank, the preparation of the rebars for the prestress beam
And preparing the formworks for the left bank pile caps
Right bank, earthworks and clearing to provide space for the retaining wall
Left bank, the preparation of the rebars for the prestress beam
And preparing the formworks for the left bank pile caps
Right bank, earthworks and clearing to provide space for the retaining wall
Subscribe to:
Posts (Atom)