PROGRESS as on 28 Jan 2014 just before their 1 Week CNY Break

Hi folks, 
Have been slack in updating the progress of our new bridge.
As on this date, the bored piles on the left bank are completed which is 3 nos of 1000mm diam and another 3 nos of 600 mm diam next to the river bank.
LEFT BANK PICS:
Round concrete spacer
 



Completed 1000mm Bored piles
 
 


Completed 600mm diam bored piles
 
 
 
RIGHT BANK:
 



Mobilised to the right bank of the river to commence the bored pile works



Some welding works on the steel pipe casing


 
Concreting of another 1000mm diam bored pile
 
 
 
 
Concreting with tremie pipe 
 
 
The weather has improved from this date, the sun was out and very hot but the ground is still wet and soggy.