Have been slack in updating the progress of our new bridge.
As on this date, the bored piles on the left bank are completed which is 3 nos of 1000mm diam and another 3 nos of 600 mm diam next to the river bank.
LEFT BANK PICS:
Round concrete spacer
Completed 1000mm Bored piles
Completed 600mm diam bored piles
RIGHT BANK:
Mobilised to the right bank of the river to commence the bored pile works
Some welding works on the steel pipe casing
Concreting of another 1000mm diam bored pile
Concreting with tremie pipe
The weather has improved from this date, the sun was out and very hot but the ground is still wet and soggy.