Thursday 28 November 2013

PROGRESS OF WORKS 28 NOV 2013 - CONCRETING OF FIRST BORED PILE FOUNDATION

There is only two major works seen today.

1.  At least two excavators are used to cut the hill slope within the road reserve to cater for the road expansion and access to the bridge at the right bank of the river. As expected, large boulders are found and rock breakers attached to one excavator is used to try and break up these rocks.

Above this slope, there is an existing private house whose owner had built a brick fence that encroached into the road reserve. This part of the fence was already removed and a new chainlink fencing is already installed at the land boundary.
Note the brick fence at the top already knocked down and replaced with a chain link fence at the reserve boundary. A retaining wall would have to be built ASAP otherwise the resident's watertank may go down the slope. He he he


2.  Pouring of the concrete into the first bored pile foundation was also carried out today.
 
 
 
 
Two videos are also linked here for your info.
 